Commencing work on one of 2 pools on the 13th floor in separate towers in Newstead.
Waterproofing and acoustic layers have been installed so that the formwork can progress.
Steelwork is now in place ready for plumbing and concreting.
Concreting has neared completion and pool will sit for 28 days to cure and allow decking works to commence.
A big thanks to the boys from Koala concrete pumping and Meales concrete pumping who teamed together to make it happen.
The tiling and decking are well underway on our pool with a view. Both pools in the towers will have waveless grates installed not only for a seamless look but also for a smoother experience when exercising.
Blue glass beads were used for the swimming pool interior, also the gutter has been epoxy painted and is now ready for the waveless grating to be installed.
The pool is now full with the waveless grate installed and an un-paralleled view of Brisbane! Time to relax!